2019 Resurfacing Town Roads - Begins April 1st  
The Town of Huntersville's annual road resurfacing will being April 1, 2019 and is anticipated to take 2-3 months to complete. Please view the attached maps of this year's Town road to be resurfaced under the Project section of the website. We ask that residents be patient during the resurfacing of their streets. The safety of our residents and the resurfacing crew is our top priority.
  
I-77 Interchange at Exit 23 and US 21 (Statesville Road) at Gilead Road Intersection
The North Carolina Department of Transportation (NCDOT) is scheduled to begin construction on the Diverging Diamond Interchange (DDI) over I-77 at exit 23 Gilead Road. The addition of a bridge over I-77 is the first part of constructing the DDI.
The US21 and Gilead Road intersection will become a superstreet with restricted left turns. This will allow through traffic to move more efficiently to and from I-77. The US21 project will also connect smaller streets like Dallas St, Hillcrest Dr and Commerce Center Dr to US21. 
Contact NCDOT representative Ms. Beverly Robinson, BRobinson@ncdot.gov 919-707-6041, for additional information or view the public handout HERE.  

Downtown Main Street Upgrades
This Capital Improvement Plan (CIP) includes new roundabouts at the North and South ends of Main Street. The Town is more than halfway completed in the property acquisition stage of the project. The project drawings are continually being updated and are scheduled to be completed fall 2019. If everything continues as scheduled, we anticipate to LET the construction of the project by the end of 2019. For an overall view of the new Main Street click HERE.

Holbrook Street Extension
The Holbrook Street Extension project will extend west from Pinewood Dr. to Dallas St. This extension of the road will tie into Marguertie Lane and allow access to the Aldi’s plaza. The Right of Way (ROW) drawings have been completed and The Town is beginning the property acquisition. An illustration of can be found HERE.

Gibson Park Drive
The objective of this project is to provide a safer street for motorists and pedestrians between US115 (Old Statesville) and Main Street. The Town will widen Gibson Park Drive to two (2) lanes with curb and gutter, and add a sidewalk on the north side. The Town is starting the property acquisition phase of the project.

Vance Road Extension at Bud Henderson Road
The Town of Huntersville desires to provide capacity improvements to Vance Road between Gilead Road and Old Bud Henderson Road. It is anticipated that the project will extend and realign Vance Road on the north side. New turning lanes and a potential traffic signal will improve the traffic flow from Gilead Road to Bud Henderson. Click here for a concept illustration.

Hambright Road at Mt.Holly-Huntersville Road
As part of a partnership with the Lake Norman Charter School, the Town added an east and westbound right-turn lane on Hambright. This project was completed in late 2018.  Click here for a finished photo.

Hambright Road at Statesville Road (U21)
As part of a partnership with the Lake Norman Charter School, left turns lanes will be added on Hambright Road at US21. Construction is anticipated to be completed in summer 2019.  Click here for an existing photo.

Mt.Holly-Huntersville at Statesville Road (U21) 
As part of a partnership with the Lake Norman Charter School, a left-turn lane from Mt.Holly Huntersville Road ramp to connect to US21 was completed in the fall of 2018.

Gilead Road Improvements from McCoy to Wynfield Creek

The improvements to this segment of Gilead Road will include the widening of the existing two-lane section to a four-lane median-divided section. The new cross section will include two (2) vehicular lanes, one (1) bicycle lane and one (1) sidewalk in each direction with median/turn lanes at each intersection. This project is in the final stages of the environmental permitting process.  Click here for the overall plan concept from the April 2nd public informational meeting.   

Patterson Road at Hambright Road
The purpose of this project is to upgrade Patterson Road to a paved curb and gutter street and provide capacity improvements at the intersection with Hambright Road. The Town will add left and right turning lanes at the Patterson Hambright intersection. The Town has completed installing the stormwater along Patterson Road. Property Acquisition for the project is currently underway.

S.Maxwell Ave and Main St. Parking Lot
The Town is going to add additional parking on S.Main St just south of Huntersville-Concord Rd. This free parking lot will be under construction in the spring of 2019.

Verhoeff Road Intersection Improvement
The Town will be installing signals at both 3-way intersections of Verhoeff Road.  The intersections of Verhoeff Rd at US115 (Old Statesville Road) and at US21 (Statesville Road) are currently stop signs. The signals are anticipated by summer 2019.