Current Projects

Huntersville Recreation Center 

Inside and Outside Rec Center Pics A soft opening will be on January 15th and the Ribbon Cutting and Grand Opening Celebration will be on January 20th.   Staff has been busy giving tours to many users groups, tournament directors and area Visitor Bureaus.  We have secured our first large tournament for the facility.  Carolina Union Volleyball will host a tournament in May that will include hosting 32 teams at the Huntersville Recreation Center.  We have numerous other leads on other tournaments and events as well.  

Veterans Park

The installation of storm water system along Main Street will be complete by the end of the week.  Veterans Park Construction Pics
The contractor will begin the installation of the underdrain system within the park next week.  Anticipated completion date for this project is early Spring.

skyview of Veterans Park

Bradford Park Turf Fields

Bradford Park Turf Project  

The contractor has begun the installation of the turf on the two fields and is anticipating to have the two turf fields completed by the end of January.